Next Cycle Count Date Falls On Non-Work Day

Jeff_MontAssoc

Active Member
When using the Cycle Count process, we are configured to set the Next Count Date (F41021.NCDJ) based on the Cycle Count Code (F4102.CYCL). The dates all calculate correctly. The issue we have is that the calculation does not take workdays vs. non-workdays into account. Is there a way to configure the system to take the shop calendar into account when calculating the Next Count Date? Even better would be to specify which shop calendar to use, but we don't want to be too greedy.

EOne 9.1
 
The only possibility appears to be customization of the MBF XT4111Z1 (F4111 EditLine).....which uses an internal function to calculate Next Count Date.

Thanks
aaro
 